Process Flow
Westwood Finishing Lines 1 and 2
LOAD: |
Parts loaded on line
Quick check for damage
Count Verification
|
Clean: |
Alkaline cleaners/Phos acid/Iron phos pre-treat
Line speed 2fpm first dry area 6 feet (Blow off area)
|
Final Dry: |
Line speed 2fpm final dry area 3 foot (knife type)
Distance to first booth 25 foot
|
Second Booth: |
9 foot wide (TOPCOAT)
Line speed 2fpm (Time in booth 4.5 minutes)
Note: These are opposing booths with rub bar swivels
|
Flash & Dry: |
220 foot, 110 min. of dry time, line speed 2fpm
Note: Material used-polyuethan requires 1.5 hours dry time until parts can be loaded and handled
This process is identical for lines 1, 1 and 3
Batch system operates the same, except no overhead line
|